Client:
Sellafield Ltd
NW Total Engineered Solutions was selected by Sellafield Ltd to manufacture and assemble a Pump Frame / Yoke Assembly, including associated pipework and specialist electrical cabling works.
The project was awarded following a competitive tender process, recognising NW Total’s proven engineering capability, quality standards and delivery performance.
3D Models
Key Project Highlights
Design Improvements
The client issued pump model had undergone a design change which affected the fit within the existing frame.
Engineering Review
NWT identified the changes and reviewed the impact on the assembly integration.
Modification Developed
Design modifications were developed to ensure teh new pump model fitted correctly and performed as intended.
Testing & Verification
Specialist electrical works including ‘Potting’ of cables and FAT testing were completed and witnessed / verified by the client.
Successful Delivery
The completed assembly was delivered with full documentation and ready for installation and use.
“NWT’s engineering expertise and attention to detail ensured we adapted to the design change, delivered a high quality solution and met all performance requirements.”